December 15, 2007 - Night Exterior
December 14, 2007 - Finishing Touches
December 3, 2007 - Plumbing
November 29, 2007 - Counters
November 28, 2007 - Ceiling
November 27, 2007 - Lawn
November 27, 2007 - Flooring
November 24, 2007 - Painting
November 10, 2007 - Vanities and Trim
November 7, 2007 - Update
October 26, 2007 - Update
October 20, 2007 - Update
October 2, 2007 - Office Corner Removal
September 29, 2007 - Shingling
September 28, 2007 - Update
September 25, 2007 - Update
September 22, 2007 - Update
September 18, 2007 - Interior Framing
September 14, 2007 - Update
September 11, 2007 - Pouring the Slab
September 7, 2007 - Bricks
September 6, 2007 - Update
September 5, 2007 - Update
August 31, 2007 - Framing
August 30, 2007, Wall Demolition
August 30, 2007 - Setting the Roof Trusses
August 29, 2007 - Framing
August 27, 2007 - Construction Loan Signing
August 27, 2007 - Removing the Roof
August 23, 2007 - Raising Walls
August 22, 2007 - Fellowship Hall Gutting
August 22, 2007 - Truss Delivery
August 20, 2007 Framing Walls
August 13, 2007 - Rough Plumbing
August 8, 2007 - Rain Delay
July 30, 2007 - Laying Block
July 27, 2007 - Pouring Footings
Digging Footings
Excavation
July 1, 2007 - Groundbreaking